Short
tricks (Time & Work)
Time
and Work is a very easy topic and at least 2 Questions are asked from this
topic in Any Exam whether it's Clerk or PO or SSC.What actually the Time and
Work Topic is all about? In simple words It's how much time a person will take
to Complete a Given Work.
Here we are providing some cases of time and work and
efficient method to solve it. Hope this would be helpful to all aspirants.
Note -: In conventional Method work is always treated as 1
Note -: In conventional Method work is always treated as 1
Example:
So if I say that a person can complete a work in 15 days that means he will do
1/15 work in one day, It's simple maths.
Now
another person does the same work in 30 days. So he will do 1/30 work in
1 day.
Now
if i ask in how many days they will complete the work together. What we gonna
do is Add their 1 day of work
like
1/15 + 1/30 = (2+1)/30 = 3/30 = 1/10
Now
this 1/10 we got is actually their 1 day work, So if they do 1/10 work in one
day then it's simple they will complete the whole work in 10 days.
Now
that was the conventional method and I believe that you all know how to solve
Questions through Conventional method.
So
now lets move on to the Faster method i.e efficiency method.
In
efficiency method the Work is not treated in numerical value, Like in
Conventional method the work is 1 but here the work is treated as percentage.
So
by common sense the work is always treated as 100%
So
when i say a person completes a work in 15 days it means he will do 100/15 %
work in 1 day i.e 6.66% work in 1 day
If
another person does the work in 30 days that means he will do 3.33% work in 1
day.
And
together they will do 6.66 + 3.33 = 9.99 or 10% work in one day So in how many
days they will do the complete work, that will be 100/10 = 10 days.
Now
it may sound difficult That we have to convert Each value in % but don't worry
you don't have to convert each value, You just have to learn all the values
till 1/30 and then it will be a cakewalk.
Now we will take Some
standard Cases Of time and work and you all are free to ask any problem if you
have in any case.
Case
1 - A does a work in X days, B does a Work in Y days In how many days they will
complete the work.
Question-
A completes the work in 10 days and B completes the work in 15 days In how many
days they will complete the work.
Conventional
Method
Work
done by A in 1 day = 1/10
Work
Done by B in 1 day = 1/15
Work
done By A & B together in 1 day = 1/10 + 1/15 = (3+2)/30 = 5/30 = 1/6
As A & B Completes
1/6 work in one day So they will complete the whole work in 6 Days.
Efficiency
method.
Efficiency of A =100/10 = 10%
Efficiency of A =100/10 = 10%
Efficiency
of B = 100/15 = 6.66%
Efficiency
of A & B Together = 10+ 6.66 = 16.66%
So
the time taken by A & B together to Complete the work will be 100/16.66 = 6
Days.
Case
-2 A can do a work in X days and B can do it Y days, In how many days the
work is completed if they work alternatively Started by A.
Now
in these type of question the person are not actually working together, what
happens in this type of question is that A works for 1 day and then on 2nd day
B work and on 3rd again A work and on Fourth again B works and so on till the
work is completed.
For
example A can do a work in 10 days B can do it 15 days and how many days they
will finish it if The work is started by A
So
again work done by A in one day = 1/10
''
'' ''
'' '' B ''
'' = 1/15
Now
the work done by Togther will be = 1/10 + 1/15 = 1/6 [ Note now this 1/6 work
is not done by them in 1 day but in 2 days Actually, See A worked for 1 day and
did 1/10 work on the second day B worked and finished the 1/15 work So in total
2 days they did 1/6 work]
So
in 2 days they did 1/6 work so in how many days they will complete the whole work,
Simple 12 days.
Efficienecy
Method
A's
Efficiency = 10%
B's
Efficiency = 6.66%
A
+ B Efficiency = 16.66%
Work
done by A and B in 2 days [ remember 2 days because they are not working
together but working alternatively] = 16.66%
So
time taken by them to complete 100% work = 100/(16.66 = 6 [ but always remember
multiply this by 2, Beacause 16.66% work is done by them in 2 days and not in 1
day.
So
The answer will be 6*2 = 12 days.
Case
3: A can do a work in X days, B can do the work Y days and A leaves after
working Z days.
Question- A
can do a work in 10 days and B can do it in 15 days, A works for 2 days and
then leaves, In how many days will the work be completed?
Now
here we can se that A leaves after 2 days that means A and B only worked for 2
days and the remaining work is done by B alone.
So
first we have to calculated the work done by A and B together in 2 days.
So
work done be A in 1 day = 1/10
""
" "
" B " " " = 1/15
Work
done by A & B together is 1 day = 1/10 + 1/15 = 1/6
Work
done by A & B together in 2 days = (1/6) * 2 = 1/3
So remaining work = 1 - 1/3 = 2/3
Now
this 2/3 work has to be done by B alone.
So
it takes 15 days for B to do Complete work, How much time it will be taken by B
to do 2/3 work ? So it will be 15*(2/3) = 10 days
So
the work will be completed in 2 + 10 days = 12 days
Efficiency
method
A's
efficiency = 10%
B's
Efficiency = 6.66%
Total
a+b = 16.66%
work
done by A and B together in 2 days = 16.66*2 = 33.33%
Work
remaining = 66.66%
time
taken by B to complete 66.66% work = 66.66/6.666 = 10 days
Total
time = 10+2 = 12 days
Case
4
A
can do a piece of Work in 10 days and B can do it in 15 days, In how many days
will the work be completed if B leaves 2 days before the completion on work.
Now
in this question B leaves before 2 days
Together
they can do the work in what = 1/10 + 1/15 = 1/6
That
means 6 Days.
That
means Together they could have completed the work in 6 days but B works only
till 4th day and The remaining work will be done by A alone
So
they worked together for 4 days in all So work done by them in 4 days = (1/6)*4
= 4/6 = 2/3
remaining
work = 1/3
Now
this 1/3 work will be done by A alone
Now
A can do the complete work in 10 days, So the time taken by him to do 1/3 work
= 10 * (1/3) = 10/3 days or 3.33 days
So
total time taken = 4+ 3.33 days = 7.33 days
Efficiency
method
A's
efficiency = 10%
B's efficiency = 6.66%
Total
= 16.66%
Work
will be completed in 6 days
Work
done in 4 days = 66.66%
remaining
= 33.33%
A
will complete the remaining in = 33.33/10 =
3.33
Total
= 4+3.33 = 7.33
Case
5: A can do a Work in X days B can Do it in Y days, In how many days The
work will get completed if B leaves 2 days before the actual completion of
work.
Question: A
can do a work in 10 days B can do it in 15 days, In how many days The work will
get completed if B leaves 2 days before the Actual Completion of Work.what is
the difference between this Actual completion of work and Completion of Work?
See
in last example the work was supposed to get completed in 6 days, So we just
Solved the question taking into consideration that B leaves 2 days before the
completion of work i.e B worked for 4 days and the rest 2 days work was don by
A alone and Completes that work in 3.33 days Total 7.33 days.
So
if i ask In this question If B left 2 days before the actual completion then it
means B should have left on 5.33 days Got it ?
Now
back to the question.
Now
just imagine that the work gets completed in x days.
So
A would work for x days[ A works for the whole time ]
And
B would work for x-2 days[ because B left 2 days before the actual completion
of work]
So
now According to Question
x/10
+ (x-2)/15 = 1 [ Beacuse work is always one ]
(3x+2x-4)/30
= 1
5x
-4 = 30
5x
= 34
x
= 6.8 days.
So
the work will be completed in 6.8 Days.
It
can also be asked That after how many days B left, So the answer would be
Simple 6.8 - 2 = 4.8 days
Efficiency
Method
A's
Efficiency = 10%
B's
Efficiency = 6.66%
Let
the no. of days be x
so
Accordring to question
10x
+ 6.66(x-2) = 100[ Work is always 100% in efficiency method ]
10x
+ 6.66x - 13.33 = 100
16.66x
= 113.33
x
= 113.33/16.66 = 6.8
Answer
= 6.8 days